If your property is listed you will need to apply for listed building consent if:

  • you want to demolish a listed building or;
  • you want to alter or extend a listed building in a manner which would affect its character as a building of special
  • architectural or historic interest.

You may also need listed building consent for any works to separate buildings within the grounds of a listed building.

If you are uncertain as to whether or not your property is listed, you can search for your property using our Interactive Map.

The best way of developing an application is through pre-application discussions with officers who can also advise on the level of information required.

For further information please refer to the Listed Buildings page on our website; in addition English Heritage offer a range of planning advice.

Planning Portal guidance notes

Requirements

The list below details supporting documents that may need to be submitted as part of your application. Please refer to each section below in order to determine whether or not you need to submit it as part of your application.

Application form

The application form is available on the Planning Portal. To access it, sign in, select ‘start new application’, then select the desired application.

When required

Always required

A completed form is always required (one copy of all application documents must be supplied if submitted by post).

What is required

Please ensure that you have completed every section of the application form before submitting. Where sections or questions are not relevant please state this on the form.

Source, policies and references

National validation requirement

Ownership certificates

When required

Always required (part of application form).

What is required

The relevant certificate must be completed, signed and dated (part of application form). Only one certificate should be completed.

  • Certificate A should be completed if the applicant is the sole owner of the land to which the application relates or holds an unexpired lease with a term of 7 or more years remaining.
  • Certificate B should be completed if the applicant is not the sole owner but knows the names and addresses of all the other owners.
    • The notice to owners [PDF] must also be completed and sent to all known owners.
    • A copy of the notice must be sent with the application to the local authority.
  • Certificate C should be completed if the applicant does not own all of the land to which the application relates and does not know the name and address of all of the owners.
    • The notice to owners [PDF] must be completed and sent to all known owners.
    • Where the owner is unknown the notice to unknown owners [PDF] needs to be published in a local newspaper.
    • A copy of the notice must be sent with the application to the local authority.
  • Certificate D should be completed if the applicant does not own all of the land to which the application relates and does not know the names and addresses of any of the owners.
    • The notice to unknown owners [PDF] needs to be published in a local newspaper.
    • A copy of the notice must be sent with the application to the local authority.

Fee

When required

No fee required for this type of application.

Location plan

When required

Always required.

What is required

This must be an up-to-date Ordnance Survey-based location plan at an appropriate scale, usually 1:1250 or 1:2500. In the case of large sites other scales may be appropriate.

The plan must show:

  • At least two named roads and all surrounding buildings or land (unless this would require a plan greater than a scale of 1:2500)
  • The application site (the whole planning unit)
  • A north point
  • The scale clearly identified

The plan used should:

  • Show OS Crown copyright
  • Not be copied from existing OS mapping, if using hand drawn maps such as standard streets
  • Show the correct licence number if you wish to print or copy maps for applications

The application site boundary must be edged clearly with a red line. A blue line should be drawn around any other land owned by the applicant, close to or adjoining the application site.

Existing site plan

When required

May be required where:

  • the proposed development involves the demolition of any existing structures
  • there are trees on site that may be impacted by the proposed development

What is required

Existing site layout plans to a recognised scale (1:100, 1:200 or 1:500 as appropriate)

The site layout plan should show:

  • the direction of north
  • a scale bar or metric measurements

In addition, the site layout plan should show the following unless these would not influence or be affected by the proposed development:

  • all the buildings, roads and footpaths on land adjoining the site including access arrangements
  • all public rights of way crossing or adjoining the site (footpath, bridleway, restricted byway or byway open to all traffic)
  • the position of all trees on the site, and those on adjacent land
  • the extent and type of any hard surfacing
  • boundary treatment including walls or fencing
  • existing car parking and turning arrangements
  • any existing bin and cycle stores

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Proposed site plan

When required

Always required.

What is required

Proposed site layout plans to a recognised scale (1:100, 1:200 or 1:500 as appropriate).

The site layout plan should show:

  • the direction of north
  • a scale bar or metric measurements

In addition, the site layout plan should show the following unless these would not influence or be affected by the proposed development:

  • all the buildings, roads and footpaths on land adjoining the site including access arrangements
  • all public rights of way crossing or adjoining the site (footpath, bridleway, restricted byway or byway open to all traffic)
  • the position of all trees on the site, and those on adjacent land
  • the extent and type of any hard surfacing
  • boundary treatment including walls or fencing
  • existing car parking and turning arrangements
  • any existing bin and cycle stores

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Existing floor plans

When required

Always required.

What is required

Drawings showing the full existing floor layout plans to an appropriate scale, usually 1:100 and with a scale bar or metric measurements included.

Drawings must show the complete building, partial drawings are not acceptable.

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Proposed floor plans

When required

Always required.

What is required

Drawings showing the full proposed floor layout plans to an appropriate scale, usually 1:100 and with a scale bar or metric measurements included.

Drawings must show the complete building, partial drawings are not acceptable.

Where applications involve the installation of mechanical and electrical building services plan or /equipment such as flues, air handling units or air conditioning, extraction, air source heat pumps, combustion appliances, the position of these should be indicated.

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Existing elevations

When required

Always required.

What is required

Detailed drawings showing the existing elevations (the appearance of the property from all sides affected by the proposal) to an appropriate scale, usually 1:100 and with a scale bar or metric measurements included.

Drawings must show the complete building, partial drawings are not acceptable.

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Proposed elevations

When required

Always required.

What is required

Detailed drawings showing the proposed elevations (showing the proposal against existing building from all sides) to an appropriate scale, usually 1:100 and with a scale bar or metric measurements included.

Drawings must show the complete building, partial drawings are not acceptable.

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Proposed roof plans

When required

Required only for complex roof structures.

What is required

The roof plan should show the shape of the roof at an appropriate scale, usually 1:50 or 1:100 and with a correct overall dimensions in metric measurements included.

Details such as the material, vents and their location should be shown.

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Source, policies and references

National validation requirement.

Interpretation and guidance notes

Roof lights should be indicated on floor plan.

Proposed detailed drawings

When required

All listed building consent applications.

What is required

Plans to the scale of not less than 1:10 and 1:2 (for details on cross-section drawings) with a scale bar or metric measurements included, to show all new doors, windows, panelling, fireplaces, plaster moulding and other decorative features where alterations are proposed to those features.

Site Levels and Cross-section drawings may be required depending on the nature of the proposal. You are advised to engage in pre-application discussions with our Conservation team before submitting your application.

Please ensure that all plans submitted as part of your application are accurately labelled and numbered.

Design and access statement

When required

  • Major development (defined as development of 10 or more dwellings (or 0.5 hectares for residential development where the number of dwellings is unknown) for the creation of more than a 1,000 sq m of floor space and where the site is greater than 1 hectare).
  • Development in a designated area (World Heritage Site or conservation area) where the proposed development consists of either one or more dwellings or a building or buildings with floor space of 100 sq m or more.
  • Applications for listed building consent.

What is required

A design and access statement should:

  • Explain the design principles and concepts that have been applied to the development
  • Demonstrate the steps that have been taken to appraise the context of the development and how the design of the development takes that context into account in relation to the proposal
  • Explain the policy adopted as to access and how policies relating to access in relevant development plan documents (DPDs) have been taken into account
  • State what, if any, consultation has been undertaken on issues relating to access to the development and what account has been taken of the outcome of any such consultation
  • Explain how specific issues which might affect access to the development have been addressed.

Statements accompanying applications for Listed Building Consent should, in addition to the above, show how they have taken account of:

  • The special architectural or historic importance of the building
  • The particular physical features of the building that justify its designation as a listed building
  • The building's setting.

Source, policies and references

National validation requirement.

Heritage statement

When required

Development affecting a heritage asset. Heritage assets are buildings, monuments, sites, places, areas or landscapes which are significant because of their historic interest.

Designated heritage assets include:

  • World Heritage Site
  • Scheduled Monument
  • Listed Building
  • Registered Park and Garden
  • Conservation Area

For new development, consideration should be given to the potential of archaeological assets.

What is required

The level of information or investigation required to support a proposal that could impact on a heritage asset needs to be proportionate to the significance of the heritage asset and the potential impact of the works proposed. Pre-application meetings are strongly recommended.

As a minimum, statements will be required to identify heritage assets and demonstrate how proposals have preserved or enhanced their significance.

Applications for works to a heritage asset to address climate change should include the information set out in Policy 63 and its supporting text.

Source, policies and references

National validation requirement.

  • CLP Policies 61, 62, 63 & Appendix G: Local heritage assets criteria and list
  • NPPF Chapter 16
  • NPPG - Conserving and enhancing the historic environment
  • Listed building descriptions
  • Conservation Area appraisals and management plans
  • Suburbs and approaches studies
  • Cambridgeshire Historic Environment Record
  • Historic England (2018) Energy efficiency and historic buildings: How to improve energy efficiency
  • Further guidance on works to heritage assets to address climate change will be included in the updated Greater

Is this page helpful?

Website feedback form
Website feedback form

For questions about a service we provide, please use our contact us form

For feedback on our new website, please use our website improvements form

Was this page helpful? (required)
Website feedback form
Tell us why (required)
Website feedback form
Tell us why (required)
Website feedback form
Prove you are a human (required)